Setelah mengetahui informasi dasar pondasi batu kali, hal yang perlu dijadikan pertimbangan sebelum pelaksanaan pondasi adalah mengetahui harga pemasangan pondasi batu kali. Berikut ini merupakan contoh analisa harga pemasangan pondasi batu kali per m3 berdasarkan acuan SNI:
1. Pasangan pondasi batu kali, campuran 1PC:3PP
Uraian |
Koef. |
Satuan |
Harga Satuan |
Jumlah |
Batu Kali 15/20 cm |
1.2 |
m3 |
130,000 |
156,000 |
Semen/ PC |
202 |
Kg |
1,300 |
262,600 |
Pasir Pasang/PP |
0.485 |
m3 |
135,000 |
65,475 |
Pekerja |
1.5 |
OH |
38,000 |
57,000 |
Tukang Batu |
0.75 |
OH |
48,000 |
36,000 |
Kepala Tukang |
0.075 |
OH |
52,000 |
3,900 |
Mandor |
0.075 |
OH |
60,000 |
4,500 |
Total |
|
|
|
585,475 |
2. Pasangan pondasi batu kali, campuran 1PC:4PP
Uraian |
Koef. |
Satuan |
Harga Satuan |
Jumlah |
Batu Kali 15/20 cm |
1.2 |
m3 |
130,000 |
156,000 |
Semen/ PC |
163 |
Kg |
1,300 |
211,900 |
Pasir Pasang/PP |
0.52 |
m3 |
135,000 |
70,200 |
Pekerja |
1.5 |
OH |
38,000 |
57,000 |
Tukang Batu |
0.75 |
OH |
48,000 |
36,000 |
Kepala Tukang |
0.075 |
OH |
52,000 |
3,900 |
Mandor |
0.075 |
OH |
60,000 |
4,500 |
Total |
|
|
|
539,500 |
3. Pasangan pondasi batu kali, campuran 1PC:5PP
Uraian |
Koef. |
Satuan |
Harga Satuan |
Jumlah |
Batu Kali 15/20 cm |
1.2 |
m3 |
130,000 |
156,000 |
Semen/ PC |
136 |
Kg |
1,300 |
176,800 |
Pasir Pasang/PP |
0.544 |
m3 |
135,000 |
73,440 |
Pekerja |
1.5 |
OH |
38,000 |
57,000 |
Tukang Batu |
0.75 |
OH |
48,000 |
36,000 |
Kepala Tukang |
0.075 |
OH |
52,000 |
3,900 |
Mandor |
0.075 |
OH |
60,000 |
4,500 |
Total |
|
|
|
507,640 |
4. Pasangan pondasi batu kali, campuran 1PC:6PP
Uraian |
Koef. |
Satuan |
Harga Satuan |
Jumlah |
Batu Kali 15/20 cm |
1.2 |
m3 |
130,000 |
156,000 |
Semen/ PC |
117 |
Kg |
1,300 |
152,100 |
Pasir Pasang/PP |
0.561 |
m3 |
135,000 |
75,735 |
Pekerja |
1.5 |
OH |
38,000 |
57,000 |
Tukang Batu |
0.75 |
OH |
48,000 |
36,000 |
Kepala Tukang |
0.075 |
OH |
52,000 |
3,900 |
Mandor |
0.075 |
OH |
60,000 |
4,500 |
Total |
|
|
|
485,235 |
5. Pasangan pondasi batu kali, campuran 1PC:8PP
Uraian |
Koef. |
Satuan |
Harga Satuan |
Jumlah |
Batu Kali 15/20 cm |
1.2 |
m3 |
130,000 |
156,000 |
Semen/ PC |
91 |
Kg |
1,300 |
118,300 |
Pasir Pasang/PP |
0.584 |
m3 |
135,000 |
78,840 |
Pekerja |
1.5 |
OH |
38,000 |
57,000 |
Tukang Batu |
0.75 |
OH |
48,000 |
36,000 |
Kepala Tukang |
0.075 |
OH |
52,000 |
3,900 |
Mandor |
0.075 |
OH |
60,000 |
4,500 |
Total |
|
|
|
454,540 |
6. Pasangan batu kosong (aanstamping)
Baca juga: Harga Tiang Pancang Dan Jenisnya
Menghitung Volume Pemasangan Pondasi Batu Kali
Setelah mengetahui analisa harga pemasangan pondasi batu kali per m3, selanjutnya anda perlu mengetahui cara menghitung volume pemasangan pondasi batu kali.
Namun, sebelum mulai menghitung volume, anda perlu mengetahui atau menyiapkan terlebih dahulu gambar denah dan detail pemasangan pondasinya. Karena untuk mengetahui volume pondasi perlu mengetahui berapa saja ukuran yang diperlukan untuk pemasangan pondasi.
Gambar denah pondasi batu kali: